
[Oct-2021] SAP C_TS422_2020 Dumps – Reduce Your Chance of Failure in C_TS422_2020 Exam
To help you achieve your ultimate goal, we suggest the actual SAP C_TS422_2020 dumps for your SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing exam preparation to use as your guideline.
NEW QUESTION 17
How would you define pegging in the context of Advanced Planning?
- A. An evaluation that is ordered according to thebill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
- B. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
- C. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
- D. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
Answer: A
NEW QUESTION 18
What does it mean for the production planner when MRP works with infinite capacities?
- A. MRP creates capacity requirements only if the work center has sufficient capacity.
- B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
- C. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
- D. MRP creates capacity requirements without checking the capacity of a work center.
Answer: D
NEW QUESTION 19
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?
- A. The cross-plant status
- B. The least restrictive status
- C. The most restrictive status
- D. The plant-specific status
Answer: C
NEW QUESTION 20
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
- A. Use batch determination.
- B. Use the material where-used report.
- C. Use the material staging report.
- D. Use the batch information cockpit.
Answer: D
NEW QUESTION 21
You need to model goods receipt processing time in Detailed Scheduling. Which modelling options do you have? Note: There are 2 correct answers to this question.
- A. Model a transportation resource in the location master.
- B. Model a handling resource in the location master and goods receipt time in the mater all master.
- C. Model a separate resource inthe production data structure.
- D. Model a resource inbound in the location master.
Answer: A,B
NEW QUESTION 22
What are the possible results of a production planning run inAdvanced Planning (PP/OS)? Note: There are 3 correct answers to this question.
- A. Scheduling agreement schedule line
- B. Purchase requisition
- C. Stock transport order
- D. Planned order
- E. Production order
Answer: A,B,D
NEW QUESTION 23
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.
- A. Individualconversion
- B. Full conversion
- C. Partial conversion
- D. Order release
Answer: B,C
NEW QUESTION 24
What is a work center hierarchy in SAP S/4HANA capacity planning?
- A. A group of alternative work centers for production, structured in hierarchy levels by prior ties
- B. A group of work centers in a production line beingused in sequence for production
- C. A group of work centers in a parallel sequence that is used to split product on quantities and work on them in parallel
- D. A group of alternative work centers providing a cumulative available capacity for production
Answer: D
NEW QUESTION 25
In your project,you have several materials that are planned by different people. How can you assign the planning responsibility?
- A. MRP planning file
- B. MRP type
- C. MRP group
- D. MRP controller
Answer: D
NEW QUESTION 26
Your project team decides to use a make-to-order planning strategy for a strategic material in discretemanufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.
- A. Production orders are created with sales order reference.
- B. Sales order-specific stock is created
- C. Sales order-specific planning run is required.
- D. Storage location MRP areas are required.
- E. Net requirements calculation is sales order-specific.
Answer: A,B,E
NEW QUESTION 27
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Creation of dependent requirements
- B. Change of the storage bin
- C. Change of the material'sprocurement type
- D. Creation of a purchasing contract
- E. Creation of a sales order
Answer: A,C,E
NEW QUESTION 28
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Work center hierarchy
- B. Resource network
- C. Operation network
- D. Setup matrix
Answer: A
NEW QUESTION 29
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The work center has several individual capacities.
- B. The Change Planning Direct on indicator is set.
- C. Alternative resources are fully occupied.
- D. The planning strategy is infinite.
Answer: A,D
NEW QUESTION 30
Duringproduction order creation, several valid production versions are found. How does the system choose the product conversion?
- A. Validity period or sales order
- B. Planned order or materialnumber
- C. Alphanumeric or quota arrangement
- D. Lot size or material cost
Answer: C
NEW QUESTION 31
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.
- A. To make the assignment of components easier
- B. To reduce the number of material masters
- C. To increase the number of planning levels
- D. To reduce the number of changes required in bills of material
- E. Tosimplify the structure of bills of material
Answer: A,D,E
NEW QUESTION 32
......
100% Free C_TS422_2020 Demo-Trial [Pdf], get it now: https://drive.google.com/open?id=1DBx3prrrej3HapObh6D5tiZNQtUXgRcp
Accurate & Verified Answers As Seen in the Real Exam here: https://www.braindumpquiz.com/C_TS422_2020-exam-material.html