Download Exam API-1169 Practice Test Questions with 100% Verified Answers
Share Latest API-1169Test Practice Test Questions, Exam Dumps
NEW QUESTION # 181
What has to be present for a shoring box to be usable.
- A. For the purpose of listing materials category
- B. Tag or documents certifying it has been inspected
- C. Identifying, documenting and oversee activity
- D. Climatic and other work condition hazards
Answer: A
NEW QUESTION # 182
Cathodic protection wire is attached to a pipe by a _______.
- A. Compression
- B. CAD weld
- C. Welding operator
- D. Design validation
Answer: C
NEW QUESTION # 183
Color used for sewers and drain lines
- A. Yellow
- B. Green
- C. Red
- D. Blue
Answer: D
NEW QUESTION # 184
Define SPCC
- A. Spill prevention, control, and containment
- B. Resource conservative in recovery act
- C. Operator qualification
- D. National pollutant discharge elimination systems
Answer: A
NEW QUESTION # 185
What is the primary issue that must be addressed with Crossing navigable waters with a natural gas pipeline?
- A. Safety concerns(general knowledge)
- B. Msds(general knowledge)
- C. A diffuser (general knowledge)
- D. The quality policy(iso 9000 3.5.8)
Answer: A
NEW QUESTION # 186
Dents have to be repaired by
- A. weight of the pipe including components
- B. Tag or documents certifying it has been inspected
- C. cutting out the entire entire diameter/cylinder of the pipe
- D. 100s of feet with additional footage shown as pulses
Answer: C
NEW QUESTION # 187
Field beveling of pipe ends by manual oxygen cutting is or is not acceptable if authorized by the company?
- A. 100%
- B. grind or sand the surface to bare metal prior to welding.
- C. Is
- D. A vertical line in the back of the ears
Answer: A
NEW QUESTION # 188
Standards for slope based on soil type
- A. 49 cfr 192.505
- B. table c-1.1 of 29 cfr 1926
- C. 29 Cfr 1926 Pg 52
- D. 29 CFR 1926 Pg 103
Answer: D
NEW QUESTION # 189
On Class 1 pipe, What percentage of pipe must be NDT tested?
- A. 10% except off-shore
- B. 15% except off-shore
- C. 35% except off-shore
- D. 100%192.243
Answer: C
NEW QUESTION # 190
Name the uniform color code colours and what they mean.
- A. Part of quality management focused on fulfilling quality requirements(ISO 9000 3.3.7)
- B. terrain features; landowner issues; road, railroad, or waterway crossing; environmental features; cultural features and protected resources (i.e. drinking water and proximity to occupied facilities)
- C. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives(ISO 9000 3.3.5)
Answer: B
NEW QUESTION # 191
What would be a discovered or potential pipeline route selection deficiencies or obstruction?
- A. A diffuser(general knowledge)
- B. An entity that includes the primary organization and any subcontractors engaged in pipeline construction covered by ARPI 1169 3.1.1
- C. terrain features; landowner issues; road, railroad, or waterway crossing; environmental features; cultural features and protected resources (i.e. drinking water and proximity to occupied facilities)
- D. Hearing protection is used when the work environment noise level exceeds 85 dbA over an 8-hour period
Answer: C
NEW QUESTION # 192
Green
- A. Sewers and drain lines
- B. Proposed excavation
- C. Potable water
- D. Communication, alarm or signal lines
Answer: A
NEW QUESTION # 193
Backhoe teeth shall be ? each time the bucket approaches the existing facility.
- A. The owner
- B. Barred or curled
- C. Owner operator
- D. Msds (general knowledge)
Answer: D
NEW QUESTION # 194
There should be enough clearance between transmission lines to allow for ____________ and _____________.
49 CFR 192.325
- A. Maintenance/protection
- B. 1.25
- C. 75 / 25
- D. 5 / 50
Answer: B
NEW QUESTION # 195
At a minimum, install and maintain temporary sediment barriers
across the entire construction right-of-way at the base of slopes greater than ________percent where the base of the slope is less than ________ feet from a waterbody
- A. 12 / 120
- B. 100 ft
- C. 10 / 100
- D. 5 / 50
Answer: D
NEW QUESTION # 196
Validation can include?
- A. Class Soil RockClass 1 30 (762) 18 (457)Class 2, 3, 4 36 (914) 24 (610)Drainage ditches of public roads and railroad crossings36 (914) 24 (610)
- B. Identifying, documenting and oversee activity
- C. Prototype testsfunctional operational teststests specified by industry standards and reg reqsField performance tests and reviews
- D. it provides proper support for the pipe and prevents damage to the pipe and its coating
Answer: C
NEW QUESTION # 197
What standard covers strength test requirements for steel pipe to operate at hoop stress of more than 30% of SMYS.
- A. 49 Cfr 202.505
- B. 49 CFR 192.505
- C. 3192.233
- D. 72/smys
Answer: D
NEW QUESTION # 198
ACI
- A. American Concrete Institute
- B. White
- C. Concrete Reinforcing Steel Institute
- D. Purple
Answer: A
NEW QUESTION # 199
If pipe has a longitudinal weld the bend must be located in the ___________
- A. Neutral axis
- B. Horizontal directional drilling
- C. Structural frame
- D. Negative deformation
Answer: A
NEW QUESTION # 200
......
Positive Aspects of Valid Dumps API-1169 Exam Dumps!: https://www.braindumpquiz.com/API-1169-exam-material.html
First Attempt Guaranteed Success in API-1169 Exam: https://drive.google.com/open?id=1pPs3d2d0PzqjegzV13yJ3A3WF6R2lXgL