SAP C-P2W22-2504 Exam Overview:
| Certification Vendor: | SAP |
|---|---|
| Exam Name: | SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing |
| Exam Number: | C-P2W22-2504 |
| Exam Duration: | 180 minutes |
| Exam Format: | Multiple Choice (Single Answer), Multiple Choice (Multiple Answers) |
| Exam Price: | $276.00 |
| Related Certifications: | SAP Certified Specialist - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing |
| Real Exam Qty: | 80 |
| Available Languages: | English |
| Certificate Validity Period: | 1 year |
| Passing Score: | 68% |
| Recommended Training: | S4HANA Cloud Private Edition PP & Manufacturing Training SAP Learning Hub |
| Exam Registration: | SAP Training & Certification Shop |
| Sample Questions: | SAP C-P2W22-2504 Sample Questions |
| Exam Way: | Online proctored or onsite at SAP authorized test centers |
| Pre Condition: | No mandatory prerequisites; recommended: basic knowledge of SAP S/4HANA and manufacturing processes, practical experience in production planning |
| Official Syllabus URL: | https://training.sap.com/certification/c_p2w22_2504-sap-certified-associate-sap-s-4hana-cloud-private-edition-production-planning-and-manufacturing/ |
SAP C-P2W22-2504 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Advanced Planning in SAP S/4HANA | 11-20% | - Tools: Alert Monitor, Detailed Scheduling Planning Board - Planning evaluation and optimization - PP/DS processes and scheduling - Master data for advanced planning |
| Demand Management in SAP S/4HANA | <=10% | - Production methods: make-to-order, make-to-stock, assembly planning - Planning strategies - Demand forecasting and planning |
| Capacity Planning | <=10% | - Finite and infinite planning - Capacity evaluation and leveling - Capacity planning table and charts |
| Material Requirements Planning (MRP) | 11-20% | - Long-term planning and master production scheduling - Lot size procedures - Basics and steps of MRP - Planning run and evaluation |
| Integration and Clean Core | <=10% | - Integration with other modules: QM, CO, MM - Clean core concept and implementation |
| Introduction to SAP S/4HANA Production Planning | <=10% | - New trends in production planning - Components and functions of production planning - Consumption-based planning vs MRP |
| Introduction to SAP S/4HANA Supply Chain Planning | <=10% | - Main components and lines of business - Motivation and background of SAP S/4HANA - SAP User Experience strategy |
| Manufacturing Operations | <=10% | - Order processing, release and confirmation - Shop floor control and execution - Material staging and goods movement - Production orders and process orders |
| Lean Manufacturing | <=10% | - Lean principles in production - Kanban and pull processing |
SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Sample Questions:
What is the difference between co-products and by-products?
Note: There are 2 correct answers to this question.
- A. Only co-products have movement type 101.
- B. Only co-products have a non-zero inventory valuation.
- C. Only co-products have movement type 531.
- D. Only co-products appear in the process or production order settlement rule.
Correct Answer: A,B 🗳️
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. For which plant can the BOM be defined?
- B. In which storage location is the BOM required?
- C. When does the BOM need to become effective?
- D. Which base unit of measure must the BOM have?
Correct Answer: A,C 🗳️
In the context of the capacity scheduling table, how do you define a pacemaker work center?
- A. By assigning it to the production version
- B. By assigning it to the capacity scheduling table
- C. By assigning it to the first operation of a routing
- D. By assigning it to the bottleneck operation
Correct Answer: A 🗳️
Which of the following are features of the clean core dashboard?
Note: There are 2 correct answers to this question.
- A. Customers can use the dashboard in the dev, test, and production tenants.
- B. It can be used in all SAP S/4HANA Cloud editions.
- C. Customers can grant access to the dashboard to partners.
- D. It can be accessed by using SAP For Me.
Correct Answer: C,D 🗳️
What is the purpose of using a low level code?
Note: There are 2 correct answers to this question.
- A. To determine the lowest explosion level at which a material occurs in all the product structures
- B. To determine the use of subitems inside the material BOM (bill of material)
- C. To determine the priority of alternative components inside the material BOM (bill of material)
- D. To determine the sequence in which materials are planned in MRP
Correct Answer: A,D 🗳️