Oracle EBS R12: Advanced Supply Chain Planning Sample Questions:
1. Determine the correct hierarchy used by the planning engine when using a priority rule.
1. Plan priority rule: Plan options form > Main tabbed region
2. Default Priority Rule: Priority rules form
3. Schedule Date: Prioritizes the demands In due date order
A) 3 , 2 , 1
B) 2 , 3 ,1
C) 1 & 2 only
D) 1, 2, 3
2. Identify four exception messages that are most likely to appear In an unconstrained plan.
A) Resource overloaded
B) Supplier Capacity overloaded
C) Orders with compression days
D) Order lead time constraint
E) Order with Insufficient lead time
F) Items with a shortage
G) Planned Order uses alternate DIM of Material/Routing
3. You are using Manufacturing Work Order Scheduling In Unconstrained Plans at your client site. Your client Is confused about some of the basic concepts, and you are asked to clarify them.
Identify two correct statements about Manufacturing Work Order Scheduling In Unconstrained Plans, which you will relate to your client.
A) In unconstrained plans, the planning engine schedules work order completion dates only later than Planning Time Fence Date.
B) Firm manufacturing orders: The plan will never recommend to cancel, reschedule, or change the Order Due Date.
C) In unconstrained plans, the planning engine schedules work order completion dates earlier than Planning Time Fence Date.
D) Firm manufacturing orders: The plan may recommend to cancel if there is no demand.
4. You are using a Material and Resource Constrained Plan. Your horizon Is the near term future.
Identify the correct question or goal for this plan.
A) How much resource capacity and material availability would I need to arrange to satisfy all anticipated demand in a timely manner?
B) Generate a feasible plan that respects material, resource, distribution, and transportation constraints.
C) Generate an optimized and executable plan based on plan objectives and material, resource, and transportation constraints.
D) How much resource capacity would I need to arrange to satisfy all anticipated demand in a timely manner?
E) How much material availability would I need to arrange to satisfy all anticipated demand in a timely manner?
5. Identify the Data Elements that Strategic Network Optimization publishes to an ASCP Plan through standard Integration.
A) Assignment Set containing Sourcing Rules to optimize your supply chain
B) Demand Class Allocation Rules based on Customer historical bookings
C) Safety Stocks to optimize Inventory levels across your enterprise
D) Optimized production schedule based on Finite capacity and material constraints
E) Global Forecast that provides an enterprisewide demand statement
Solutions:
Question # 1 Answer: D | Question # 2 Answer: C,D,F,G | Question # 3 Answer: C,D | Question # 4 Answer: A | Question # 5 Answer: A |