Holding the PMI-PBA certification makes a professional highly recognized and respected. With this certificate, the successful candidates can explore numerous opportunities in the domain of business analysis. The job roles that they will be able to take up include a Business Analyst, a Business Systems Analyst, an IT Senior Business Analyst, a Scrum Master, a Project Manager, a Business Development Analyst, a Business Process Analyst, and a Lead Business Analyst, among others. On average, the salary for a Business Analyst ranges from $50,000 to $98,000 per annum. However, the actual remuneration can vary depending on the specific job title and other factors.
NEW QUESTION 54
An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?
- A. Change control processes
- B. Impacts on requirements baseline
- C. External dependencies
- D. Deliverables to be produced
Answer: B
NEW QUESTION 55
The business analyst has worked with the stakeholders to capture their views of organizational improvement for the company. It would be best to align these with the:
- A. project charter
- B. requirements traceability matrix
- C. work breakdown structure
- D. vision/scope document
Answer: D
NEW QUESTION 56
Company A would like to enter into a new market. The business analyst has been assigned lo a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?
- A. Hire external subject matter experts for the core project team.
- B. Ask the sponsor for more resources.
- C. Ask the developer's team manager for more resources
- D. Review the business case to reconsider the project.
Answer: A
NEW QUESTION 57
A company is working on implementing a software application. They are converting their complex, m-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?
- A. MoSCoW
- B. Feasibility analysis
- C. Requirements traceability
- D. Interface analysis
Answer: D
NEW QUESTION 58
What should a business analyst do after discovering that two solution requirements conflict?
- A. Communicate the conflict to stakeholders and facilitate a resolution.
- B. Perform an impact analysis and propose a lower-cost alternative,
- C. Update the requirements baseline and upload it to the project repository.
- D. Consult the sponsor(s) and log the constraint.
Answer: A
Explanation:
Explanation/Reference: https://flylib.com/books/en/4.445.1.232/1/
NEW QUESTION 59 
A company uses a prioritization range of 1-10. in which 10 represents the highest or best. According to the information from the table, which option should the business * analyst recommend?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: A
NEW QUESTION 60
A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?
- A. MoSCoW
- B. Budget analysis
- C. Time-boxing
- D. Multivoting
Answer: A
NEW QUESTION 61
While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis favors a custom-developed solution, either built internally or using contract labor.
To prepare the recommendation, what should the business analyst do?
- A. Perform solution evaluation
- B. Formulate a weighted-ranking matrix.
- C. Recommend the SVP's choice, as It is most likely to be adopted.
- D. Review the stakeholder analysis.
Answer: B
NEW QUESTION 62
The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.
Which technique should the business analyst have followed to ensure consensus?
- A. The business analyst should have performed a complete review of each requirement with one of the stakeholders' peers before the meeting
- B. The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.
- C. The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.
- D. The business analyst should have invited the key stakeholders to the meeting.
Answer: B
NEW QUESTION 63
A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.
Which metrics tool should the business analyst use to record the results?
- A. Sales and marketing
- B. Business completion
- C. Customer
- D. Focus group
Answer: B
NEW QUESTION 64
Which technique or tool is used to obtain acceptance of the delivered product?
- A. Inspection
- B. Expert judgment
- C. Facilitated workshops
- D. Contextual inquiry
Answer: A
Explanation:
Explanation/Reference: https://www.pmi.org/learning/library/practical-quality-management-project-managers-16
NEW QUESTION 65
A type of requirements document that would be the most valuable to a database administrator would be:
- A. an object diagram.
- B. a data flow diagram.
- C. an entity relationship diagram
- D. a business process diagram.
Answer: C
NEW QUESTION 66
During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?
- A. Requirements baseline
- B. Requirements management tool
- C. Requirements cards
- D. Requirements traceability matrix
Answer: D
NEW QUESTION 67
Which of the following would be the best practice in product validation?
- A. The measurement of the requirement should be based on the average of two or more evaluations.
- B. There should be two separate measurements for evaluating each functional requirement.
- C. The evaluation criteria should be the same as what was used to measure the requirement.
- D. Two or more testers should test the product using the same test cases so that their evaluations are consistent.
Answer: C
NEW QUESTION 68
The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.
Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid recommendation"?
- A. Gap
- B. Cost-benefit
- C. Risk
- D. SWOT
Answer: B
NEW QUESTION 69
Which of the following best describes the function of the requirements baseline?
- A. Defines how the project will be scheduled.
- B. Tracks the progress of requirements documentation.
- C. Provides the basis for the development scope.
- D. Controls the product development and evolution.
Answer: B
Explanation:
Explanation/Reference: https://www.jamasoftware.com/blog/defining-requirement-baseline/
NEW QUESTION 70
The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?
- A. How is the organizational chart structured?
- B. Which stakeholders have the most influence?
- C. Which functional areas are impacted?
- D. What is the business need?
Answer: D
NEW QUESTION 71
A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.
What is the best approach to resolve this issue?
- A. Suggest re-estimating the requirement and following the change control process.
- B. Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.
- C. Meet with the customer and apologize for misunderstanding the busmess's need.
- D. Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.
Answer: A
NEW QUESTION 72
A business analyst has been assigned to ProjectY. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the business need?
- A. Reliability matrix
- B. Traceability matrix
- C. Requirements management plan
- D. Requirements package
Answer: A
Explanation:
Explanation/Reference: https://www.linkedin.com/pulse/relationships-between-requirements-design-elements-gurjar-cbap
NEW QUESTION 73
A company is developing a new product for a customer and is required to verify and validate the product against the customer's acceptance test plan and requirements. The product was successfully verified against the acceptance test criteria, but the customer does not believe that the product meets the requirements.
This occurred because the customer's acceptance test plan:
- A. was not formally accepted by the company.
- B. was not included in the work breakdown structure.
- C. did not have measurable and testable requirements.
- D. was incomplete and missing requirements.
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION 74
A key component of the business analyst's role during acceptance testing is to:
- A. delegate execution of acceptance testing and defect identification to users.
- B. execute all acceptance tests on behalf of the user community.
- C. act as a resource only when users encounter difficulties while performing tests.
- D. assist the quality assurance department by defining acceptance criteria.
Answer: C
Explanation:
Explanation/Reference: https://www.businessanalystlearnings.com/blog/2015/10/21/the-role-of-business-analysts-in-user- acceptance-test-sessions-how-to-identify-test-cases
NEW QUESTION 75
The business analyst has been assigned to a project which delivers functionality for a much larger solution.
The project has many requirements but has not received adequate funding. In addition, the stakeholders' views conflict.
Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?
- A. Stakeholder register, decision tree, and capability matrix
- B. Traceability matrix, context diagrams, and scope document
- C. Weighted matrix, process flow, and organizational chart
- D. Decision trees, weighted matrix, and context diagrams
Answer: D
NEW QUESTION 76
Which of the following can be used to determine if requirements align to the product's objectives?
- A. Context diagrams
- B. Business use cases
- C. Activity network diagrams
- D. Five Whys
Answer: B
NEW QUESTION 77
......