NEW QUESTION # 38
How can you update the degree of processing for an activity?

  • A. By confirming the activity
  • B. By using results analysis
  • C. By changing the activity
  • D. By scheduling the activity

Answer: A


NEW QUESTION # 39
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?

  • A. Calculation of actual values
  • B. Creation of purchase orders
  • C. Activity allocation
  • D. Goods receipt for purchase orders

Answer: B


NEW QUESTION # 40
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

  • A. You can always maintain the actual start and finish date of a WBS element
  • B. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
  • C. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
  • D. You can only maintain the actual start of a WBS element if the finish date is not maintained

Answer: A,C

Explanation:
If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially released", which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 41
You are working with networks and WBS elements. Which of the following statements applies

  • A. You can reassign an activity from one network to another
  • B. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
  • C. You have to maintain a network profile in the project profile
  • D. You can assign the network header to multiple WBS elements

Answer: C

Explanation:
One of the statements that applies to working with networks and WBS elements is that you have to maintain a network profile in the project profile. A network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. A project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. You have to assign a network profile to a project profile in order to create networks within a project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 42
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. Extended capacity evaluation
  • B. Capacity load work center view
  • C. Individual overview capacity requirements
  • D. None
  • E. Structure overview

Answer: C


NEW QUESTION # 43
The various work packages in the project are described as individual______________. Choose the correct answer.

  • A. Activities
  • B. WBS elements
  • C. Tasks
  • D. Project definitions

Answer: B


NEW QUESTION # 44
You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?

  • A. Missing material availability
  • B. Missing budget for material components
  • C. Missing authorizations to release material components
  • D. Missing reservations for material components

Answer: A


NEW QUESTION # 45
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.

  • A. Material master
  • B. WBS element
  • C. Network activity
  • D. BOM item

Answer: C,D


NEW QUESTION # 46
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.

  • A. You can only maintain the actual start of a WBS element if the finish date is not maintained.
  • B. You can always maintain the actual start and finish date of a WBS element.
  • C. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
  • D. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".

Answer: C,D


NEW QUESTION # 47
Which object is used to allocate the costs from a claim to the project structure?

  • A. Claim
  • B. Internal order
  • C. WBS element
  • D. Network activity

Answer: D


NEW QUESTION # 48
Resources
You Want assign milestone to WBS element? For what can you use these milestone.

  • A. For trend analysis.
  • B. To create standard network
  • C. To start workflow task.
  • D. To set an actual finish date for WBS element-

Answer: A


NEW QUESTION # 49
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?

  • A. Assign One production order to a sales order
  • B. Assign Several production orders to a sales order
  • C. Assign a sales order to a project with appropriate hierarchy levels.
  • D. Assign a network to a sales order

Answer: C

Explanation:
To avoid unnecessary stock cost, you can assign a sales order to a project with appropriate hierarchy levels. This means that you can create a project structure that matches the multilevel production environment with bill of material and routing. You can assign a sales order item to a WBS element that represents the finished product and assign production orders to WBS elements that represent the semi-finished products. This way, you can use project stock to manage the materials required for the project and avoid creating inventory for intermediate products. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002


NEW QUESTION # 50
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.

  • A. The item category of the materials is set tstock item.
  • B. The item category of the materials is set tnon-stock item.
  • C. The procurement type in the material master is set to in-house Production.
  • D. The material have no material number.

Answer: A,C


NEW QUESTION # 51
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

  • A. Shift activities backward or forward on the time axis where more capacities are available
  • B. Trigger automatic capacity leveling inside the project planning board
  • C. Maintain subordinate internal activity elements assigned to other work centres
  • D. Increase the capacities of the work center in the project planning board.

Answer: A,C


NEW QUESTION # 52
Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?

  • A. Use mass change within the project Builder (CJ20N).
  • B. Double the capacity in the work center.
  • C. Use mass change (CNMASS) in the project system.
  • D. Double the work of each internal activity, one after another, in the project Builder.

Answer: C


NEW QUESTION # 53
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.

  • A. An activity-account-assigned network that is assigned to a sales order item
  • B. Released WBS elements, activities, and/or activity elements
  • C. A dynamic item processor (DIP) profile with the appropriate settings
  • D. A header-account-assigned network that is assigned to a sales order item

Answer: B,C


NEW QUESTION # 54
Dates
How are earliest dates and latest dates of activities schedule?

  • A. Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.
  • B. Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.
  • C. Earliest dates and latest dates are scheduled by forward scheduling.
  • D. Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.

Answer: A


NEW QUESTION # 55
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

  • A. The materials must allow sales order or project stock
  • B. The exact lot size procedure must be used
  • C. The procurement type of the material must be internal
  • D. An MRP group must be assigned

Answer: B,C


NEW QUESTION # 56
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

  • A. Schedule Manager
  • B. Project Builder
  • C. Project planning board
  • D. Easy Cost Planning

Answer: B,C


NEW QUESTION # 57
......


To prepare for the SAP C-TS412-2021 certification exam, candidates can take advantage of a variety of resources, including SAP training courses, online tutorials, and practice exams. They can also gain practical experience by working on SAP S/4HANA Project Systems projects. With the right preparation and dedication, candidates can pass the SAP C-TS412-2021 certification exam and take their careers to the next level.

 

Updated SAP C-TS412-2021 Dumps – PDF & Online Engine: https://www.braindumpquiz.com/C-TS412-2021-exam-material.html

C-TS412-2021.pdf - Questions Answers PDF Sample Questions Reliable: https://drive.google.com/open?id=19yg2iifHCmstFv5jAEIA0Mwnu9tV6U_O