SAP C_TSCM62_64 Exam Overview:
| Certification Vendor: | SAP |
|---|---|
| Exam Name: | SAP Certified Application Associate - Order Fulfillment with SAP ERP 6.0 EHP4 |
| Exam Number: | C_TSCM62_64 |
| Real Exam Qty: | 80 (approx.) |
| Exam Duration: | 180 minutes |
| Related Certifications: | SAP Certified Application Associate - Sales and Distribution (SD) SAP ERP 6.0 EHP4 Sales & Distribution |
| Passing Score: | Approximately 60% (SAP standard, may vary) |
| Exam Format: | Multiple choice, Multiple response, Scenario-based questions |
| Available Languages: | English |
| Certificate Validity Period: | SAP certification validity typically 2–3 years (policy dependent; may require recertification for newer SAP programs) |
| Exam Price: | USD 500-600 (varies by country and SAP partner testing center) |
| Sample Questions: | SAP C_TSCM62_64 Sample Questions |
| Exam Way: | Computer-based exam delivered via SAP-authorized testing centers or online proctoring (e.g., Pearson VUE) |
| Pre Condition: | Basic knowledge of SAP ERP navigation and Sales and Distribution (SD) processes is recommended; no mandatory prerequisites |
| Official Syllabus URL: | https://training.sap.com/certification/ |
SAP C_TSCM62_64 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Billing and Invoicing | - Invoice processing
|
| Availability Check and Credit Management | - Order fulfillment controls
|
| Master Data in SD | - Core master data elements
|
| Shipping and Logistics Execution | - Delivery processing
|
| Sales Order Processing | - Order management in SAP SD
|
| Pricing and Conditions | - Pricing procedure
|
SAP Certified Application Associate - Order Fulfillment with SAP ERP 6.0 EHP4 Sample Questions:
Which of the following criteria can be used to determine the schedule line category?
- A. Item category group and strategy group
- B. MRP type and shipping point
- C. Item category and MRP type
- D. Item category and document type
Correct Answer: C 🗳️
In which of the following situations is forward scheduling performed at the item level during order entry? Note: There are 2 correct answers to this question.
- A. When the transportation planning or material availability date determined by the backward scheduling is in the past.
- B. If the system could not determine a replenishment lead time from the material master.
- C. When the loading date determined by the backward scheduling falls on a public holiday.
- D. When the available quantity of the material is not sufficient to meet the material availability date determined by the backward scheduling.
Correct Answer: A,D 🗳️
You have been asked to change a process so that during sales invoicing, any manually changed pricing elements in the pricing procedure of the sales document are copied from the sales order to the billing document unchanged, but the other automatically determined conditions are redetermined. In which of the following places is this controlled?
- A. In the item category of sales order item
- B. In the condition type
- C. In copy control at item level
- D. In the billing type
Correct Answer: C 🗳️
Which of the following SAP NetWeaver components ensures company-wide unification of data and information in heterogeneous IT environments?
- A. Master Data Management
- B. Knowledge Management
- C. Business Warehouse
- D. Enterprise Portal
Correct Answer: A 🗳️
Which of the following can be identified as the most likely cause of a delivery split in a collective delivery run?
- A. The sales order line items have the same route and the same shipping point, but different ship to parties.
- B. The shipping conditions of two separate items in the sales order differ from one another.
- C. The loading group of one of the items in the sales order differs from the others.
- D. The physical weight of the total line items exceeds the capacity of the truck that is being used to deliver the product.
Correct Answer: A 🗳️