SAP C-TS420-1809 Exam Overview:
| Certification Vendor: | SAP |
| Exam Name: | SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing (1809) |
| Exam Number: | C_TS420_1809 |
| Passing Score: | 60% |
| Related Certifications: | SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing |
| Exam Price: | USD 550 |
| Real Exam Qty: | 80 |
| Exam Duration: | 180 minutes |
| Available Languages: | English |
| Exam Format: | Multiple Choice, Multiple Response |
| Certificate Validity Period: | Version-specific SAP certification (valid until exam retirement or superseded release) |
| Sample Questions: | SAP C-TS420-1809 Sample Questions |
| Exam Way: | SAP Certification Hub online proctored exam or SAP-authorized test center. |
| Pre Condition: | No mandatory prerequisite certification. SAP recommends practical project experience and training in SAP S/4HANA Production Planning and Manufacturing. |
| Official Syllabus URL: | https://training.sap.com/certification/c_ts420_1809-sap-certified-application-associate---sap-s4hana-production-planning-and-manufacturing-g/ |
SAP C-TS420-1809 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Production Planning Integration | 8% - 12% | - Cross-Functional Integration
|
| Topic 2: Material Requirements Planning | 12% - 16% | - MRP Procedures
|
| Topic 3: Demand Management | 8% - 12% | - Demand Planning
|
| Topic 4: Capacity Planning | 8% - 12% | - Capacity Management
|
| Topic 5: Process Orders | 8% - 12% | - Process Manufacturing
|
| Topic 6: Production Orders | 12% - 16% | - Order Processing
|
| Topic 7: Monitoring and Analytics | < 8% | - SAP Fiori and Reporting
|
| Topic 8: Lean Manufacturing | 8% - 12% | - Repetitive Manufacturing
|
| Topic 9: Master Data in Manufacturing | 12% - 16% | - Manufacturing Master Data
|
SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing (1809) Sample Questions:
1. Which SAP solutions are part of the Digital Value Network portfolio?
There are 3 correct answers to this question.
Response:
A) Concur
B) SAP Fieldglass
C) SAP Human Capital Management
D) SAP Hybris
E) SAP Visual Enterprise
2. At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?
Please choose the correct answer.
Response:
A) The requirements date occurs that of a firmed planned receipt
B) The requirements date occurs before that of a firmed planned receipt
C) The requirement no longer exists
D) A firmed planned receipt cannot be rescheduled
3. A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Response:
A) Infinite resource and infinite strategy
B) Finite resource and finite strategy
C) Finite resource and infinite strategy
D) Infinite resource and finite strategy
4. The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
Response:
A) Selection Method
B) Purchasing Info Record
C) Production Version
D) Contract
5. What are prerequisites for using batch derivation?
There are 2 correct answers to this question.
Response:
A) Batch determination selection conditions
B) Receiver-sender relationships
C) Process instructions
D) Batch where-used list
Solutions:
| Question # 1 Answer: A,B,D | Question # 2 Answer: B | Question # 3 Answer: B | Question # 4 Answer: C | Question # 5 Answer: B,D |