SAP C-TS420-1809 Exam Overview:
| Certification Vendor: | SAP |
|---|---|
| Exam Name: | SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing (1809) |
| Exam Number: | C-TS420-1809 |
| Passing Score: | 60% |
| Related Certifications: | SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing |
| Exam Price: | USD 550 |
| Real Exam Qty: | 80 |
| Exam Duration: | 180 minutes |
| Available Languages: | English |
| Exam Format: | Multiple Choice, Multiple Response |
| Certificate Validity Period: | Version-specific SAP certification (valid until exam retirement or superseded release) |
| Sample Questions: | SAP C-TS420-1809 Sample Questions |
| Exam Way: | SAP Certification Hub online proctored exam or SAP-authorized test center. |
| Pre Condition: | No mandatory prerequisite certification. SAP recommends practical project experience and training in SAP S/4HANA Production Planning and Manufacturing. |
| Official Syllabus URL: | https://training.sap.com/certification/c_ts420_1809-sap-certified-application-associate---sap-s4hana-production-planning-and-manufacturing-g/ |
SAP C-TS420-1809 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Production Planning Integration | 8% - 12% | - Cross-Functional Integration
|
| Topic 2: Material Requirements Planning | 12% - 16% | - MRP Procedures
|
| Topic 3: Demand Management | 8% - 12% | - Demand Planning
|
| Topic 4: Capacity Planning | 8% - 12% | - Capacity Management
|
| Topic 5: Process Orders | 8% - 12% | - Process Manufacturing
|
| Topic 6: Production Orders | 12% - 16% | - Order Processing
|
| Topic 7: Monitoring and Analytics | < 8% | - SAP Fiori and Reporting
|
| Topic 8: Lean Manufacturing | 8% - 12% | - Repetitive Manufacturing
|
| Topic 9: Master Data in Manufacturing | 12% - 16% | - Manufacturing Master Data
|
SAP Certified Application Associate – SAP S/4HANA Production Planning and Manufacturing (1809) Sample Questions:
Which SAP solutions are part of the Digital Value Network portfolio?
There are 3 correct answers to this question.
Response:
- A. Concur
- B. SAP Fieldglass
- C. SAP Human Capital Management
- D. SAP Hybris
- E. SAP Visual Enterprise
Correct Answer: A,B,D 🗳️
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?
Please choose the correct answer.
Response:
- A. The requirements date occurs that of a firmed planned receipt
- B. The requirements date occurs before that of a firmed planned receipt
- C. The requirement no longer exists
- D. A firmed planned receipt cannot be rescheduled
Correct Answer: B 🗳️
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Response:
- A. Infinite resource and infinite strategy
- B. Finite resource and finite strategy
- C. Finite resource and infinite strategy
- D. Infinite resource and finite strategy
Correct Answer: B 🗳️
The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
Response:
- A. Selection Method
- B. Purchasing Info Record
- C. Production Version
- D. Contract
Correct Answer: C 🗳️
What are prerequisites for using batch derivation?
There are 2 correct answers to this question.
Response:
- A. Batch determination selection conditions
- B. Receiver-sender relationships
- C. Process instructions
- D. Batch where-used list
Correct Answer: B,D 🗳️
We're so confident of our products that we provide no hassle product exchange.