SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1709) Sample Questions:
1. Which data object can be updated with the scheduling results of a routing?
Please choose the correct answer.
Response:
A) Material master
B) Production version
C) MRP profile
D) Production scheduling profile
2. Which SAP solutions are part of the Digital Value Network portfolio?
There are 3 correct answers to this question.
Response:
A) Concur
B) SAP Fieldglass
C) SAP Human Capital Management
D) SAP Hybris
E) SAP Visual Enterprise
3. The pegging situation was changed because of an MRP heuristic run. What is a capability of dynamic
pegging?
Response:
A) It propagates changed sales order priorities to the pegged planned orders
B) It links receipts from an alternative location in case of a shortage in the default location
C) It enables the propagation of network alerts across the bill of materials structure
D) It replaces fixed pegging relationships unless they have been created for stock
4. In which customizing activity do you set up automatic routing selection for production orders?
Please choose the correct answer.
Response:
A) Define production scheduling profile
B) Define scheduling parameters for production orders
C) Define selection profiles
D) Define order-type-dependent parameter
5. What are some of the advantages of using Kanban?
There are 2 correct answers to this question.
Response:
A) It is mostly accomplished by manual postings
B) It is a simplified form of production control
C) Replenishments are created close to the actual need
D) Replenishments are based on centralized planning
Solutions:
| Question # 1 Answer: A | Question # 2 Answer: A,B,D | Question # 3 Answer: B | Question # 4 Answer: D | Question # 5 Answer: B,C |