Oracle 1Z0-129 Exam Overview:
| Certification Vendor: | Oracle |
|---|---|
| Exam Name: | Primavera P6 2021 Enterprise Project Portfolio Management |
| Exam Number: | 1Z0-129 |
| Exam Duration: | 90 minutes |
| Real Exam Qty: | 55 |
| Exam Format: | Multiple Choice, Multiple Answer |
| Certificate Validity Period: | Version-specific, no expiration |
| Passing Score: | 64% |
| Available Languages: | English |
| Exam Price: | USD 245 |
| Recommended Training: | Oracle University: Primavera P6 EPPM 2021: Implementation and Administration |
| Exam Registration: | Pearson VUE Oracle Education |
| Sample Questions: | Oracle 1Z0-129 Sample Questions |
| Exam Way: | Online proctored or onsite test center via Pearson VUE |
| Pre Condition: | No mandatory prerequisites; recommended: 6+ months hands-on experience with Primavera P6 EPPM, understanding of project management principles |
| Official Syllabus URL: | https://education.oracle.com/primavera-p6-2021-enterprise-project-portfolio-management/pexam_1Z0-129 |
Oracle 1Z0-129 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Baseline and Progress Management | 10% | - Use timesheets and progress entry methods - Update project progress, actuals, and remaining work - Analyze performance and compare against baseline - Create and maintain baselines |
| Resource and Role Management | 15% | - Define resources, roles, and resource calendars - Assign resources and roles to activities - Manage resource curves and availability - Perform resource leveling and analyze allocation |
| Overview and Navigation | 10% | - Navigate user interface, menus, and views - Understand P6 EPPM architecture and components - Set user preferences and application settings |
| Risk and Issue Management | 5% | - Log and resolve issues and changes - Identify, assess, and mitigate risks |
| Project Creation and Structure | 15% | - Develop Work Breakdown Structure (WBS) - Define activities, activity codes, and calendars - Create new projects and configure project settings - Establish project hierarchy and relationships |
| Customization and Administration | 5% | - Customize views, layouts, and reports - Manage security, users, and global data definitions |
| Portfolio and Program Management | 10% | - Create and manage portfolios and programs - Manage multiple projects and cross-project relationships - Use dashboards, reports, and portfolio analysis |
| Cost Management | 10% | - Assign costs and expenses to activities and resources - Calculate and analyze project costs, budgets, and variances - Define cost accounts, expense categories, and cost types |
| Scheduling and Logic | 20% | - Define activity relationships and constraints - Perform scheduling calculations and analyze critical path - Understand duration types, percent complete types, and calculation methods - Apply advanced scheduling techniques and lead/lag values |
Oracle Primavera P6 2021 Enterprise Project Portfolio Management Sample Questions:
When assigning a user to a User Interface view, deselecting the Allow Editing check box restricts the user's ability to .
- A. edit his or her password
- B. edit his or her Resource Profile
- C. edit the User Interface View
- D. edit project data in the view
Correct Answer: D 🗳️
Identify a relevant use case for applying a Must Finish By date to a project.
- A. Compare Scheduled Finish to Must Finish By dates to negotiate realistic Finish dates
- B. Apply Must Finish By dates to shorten the duration of the schedule
- C. Compare Must Finish By date to Actual Finish Date to negotiate realistic Finish dates
- D. Apply Must Finish By dates to build case for requesting resources
Correct Answer: C 🗳️
Identify the true statement regarding a Capacity Planning chart.
- A. The Capacity Planning chart displays unstaffed assignments over time.
- B. The Capacity Planning chart displays project allocation over time.
- C. The Capacity Planning chart displays resource allocation over time.
- D. The Capacity Planning chart displays role allocation over time.
Correct Answer: B 🗳️
Identify one function granted to On Hold users.
- A. They can be added to workflows.
- B. They can initiate Business Processes.
- C. They can log into Unifier.
- D. They can create Business Processes.
Correct Answer: A 🗳️
You are a project manager with a required monthly update cycle. You have marked actual start and actual finish dates for your Physical % complete activities, with % complete calculated from activity steps. You schedule and summarize your project plans. However, your activities are not showing 100% complete. What is the problem?
- A. You must refresh the view in the web to view the changes.
- B. You did not save the changes made to the activities.
- C. Your security does not allow you to update Activity Status.
- D. You have not completed each of the activity steps.
Correct Answer: A 🗳️
Viewing page 1 out of 45 pages.
Viewing questions 1-5 out of 221 questions.