IBM PureFlex Technical Expert V1 Sample Questions:
1. A client uses a PureFlex With a Flex System V7000 control enclosure. They want to add more storage capacity to the current system but there is no free bay space in the current class.
What is the recommended solution for this scenario?
A) Add a Flex System V7000 control enclosure to the current system using another chassis
B) Add a Flex System V7000 expansion enclosure to the current system using another chassis.
C) Add a Storwize V7000 expansion enclosure to the current system
D) Add a Storwize V7000 control enclosure to the current system
2. A client is considering Hyper-V and VMware for their virtualized x86 nodes in a proposed PureFlex solution. The client wants to implement automation with the PureFlex solution. What FSM functions are only available on VMware?
A) Create, edit, and delete virtual servers
B) Start, stop, restart, and suspend virtual servers
C) Relocate virtual servers
D) Capture and deploy workloads
3. On a PureFlex system, how can the FSM be restored from a previous backup?
A) The FSM can only be restored from a backup on the local hard drive. This is the only location where a backup can be stored.
B) The FSM can be restored from a backup on the local hard drive, a supported USB device or a Secure FTP Server.
C) The FSM can only be restored on a non-configured FSM. The FSM must be reinstalled/reset and then the backup can be installed from thelocal hard drive.
D) The FSM cannot be backed up completely; only specific information like EAPs can be saved. It must be reinstalled and the startup wizard runagain.
4. The client is consolidating the critical SAP infrastructure on Power p260 nodes. Which configuration will support the dual VIOS configuration required by this client?
A) p260 node with 2 x EN4054 4-port 10Gb Ethernet adapters
B) p260 node with 1 x EN4054 and 1 x FC3172 2-port 8Gb Fibre Channel adapter
C) p260 node with 2 x CN4058 8-port 10Gb Converged adapters
D) p260 node with 1 x EN4054 and 1 x FC5052 2-port 16Gb Fibre Channel adapter
5. 
The current phase of their modernization effort is focused on upgrading their servers. Which action best addresses the client's requirement?
A) Propose IBM's Flex nodes that support all appropriate connectivity options to connect to the existing storage
B) Find out what Cisco, HP, and Dell are bidding and build an IBM Flex solution to match them at lower costs
C) Arrange a visit to the closest IBM Briefing Center so they can see the latest releases of the compute nodes
D) Propose the x222 Flex nodes because they will provide the most cost effective solution
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: C | Question # 3 Answer: B | Question # 4 Answer: C | Question # 5 Answer: A |